Project Name | Centropod |
Developer | RP East Pte Ltd |
Architect | TBA |
Site Area | TBA |
No. Of Units | 108 Commercial Shops, 9 Restaurants and 75 Offices |
District | 14 |
Tenure | Freehold |
Expected TOP | 2015 |
Carpark | TBA |
Unit Types | |
Foundation
Bored Piles and/or Concrete Piles and/or Steel H Piles and/or Raft Foundation.
Substructure & Superstructure
Reinforced concrete and/or steel frame.
Wall
• External: Common clay bricks and/or precast panel and/or reinforced concrete generally
• Internal: Common clay bricks and/or cement blocks and/or light weight blocks and/or precast panels and/or reinforced concrete and/or dry wall generally
Roof
• Flat Roof: Reinforced concrete roof with waterproofing system and insulation.
• Pitch Roof: Metal roofing sheet with insulation and Integrated Grid-Connected Photovoltaic power system and skylight panel.
Ceiling
• For Shop, Restaurant and Office: Off-form concrete surface and/or plaster board ceiling and/or skim coat where applicable
Note:
a) Office units have a high floor-to-floor height of 5m. The internal ceiling height is 4.4m to 4.7m, except for Office units #05-07 to #05-10, which have ceiling heights of 3.5m to 4.7 m; and #04-07 to #04-10, which have ceiling heights of 4m to 4.7m.
a) Shop and Restaurant units have a ceiling height of between 4m to 4.7m.
Finishes
Internal Wall Finishes:
• For Shop, Restaurant and Office: Cement and sand plaster with emulsion paint where applicable
Internal Floor Finishes:
• For Shop, Restaurant and Office: Concrete surface in trowel finish
• A/C Ledges: Cement and sand screed finish
Windows
For Office: Aluminium framed glass windows where applicable.
Note:
a) All aluminium frames shall be powder-coated and/or natural anodized finish.
b) All windows are either side-hung, top-hung or bottom-hung or sliding or any combination of the above mentioned.
c) All glazing below 1m from floor level shall be tempered or laminated glass.
d) All glazing to be plain float and/or tinted glass.
Doors
• For Shop and Restaurant: Metal roller shutter
• For Office: Approved fire-rated door c/w ironmongery
Sanitary Fittings
• For Restaurant: 1 stainless steel sink c/w tap
• For Shop and Office: 1 wall-hung washbasin c/w tap
Electrical Installation
• 415V Three phase, 60Amp, for all Restaurant units with individual metering
• 230V Single phase, 60Amp, for all Shop and Office units with individual metering
Note:
a) Electrical wiring will be in concealed conduits where possible. Where there is a false ceiling, the electrical wiring will be in surface mounted conduit in the ceiling space.
b) The routing of services within the shop, restaurant and office units shall be at the sole discretion of the Architect and Engineer.
c) Cable-readiness to comply with authorities’ requirements.
Network
a) Cable network provided
b) Telephone point provided with unit
c) Wi-Fi provided on attic storey
Lightning Protection
Lightning Protection System shall be provided in accordance with the Singapore Standard SS555.
Painting:
• Internal Walls: Emulsion paint
• External Walls: Weather shield paint and/or spray textured coating at selected areas only
Waterproofing
Waterproofing to communal swimming pool, pool deck and toilets.
1st Storey Driveway
• Reinforced concrete with powder float finish and/or interlocking pavers and/or heavy-duty tiles and/or aeration slabs at selected areas only.
Basement Car Park and Ramp
Concrete finished with floor hardener and/or heavy-duty tiles at selected areas only.
Recreational Facilities
3rd Floor Communal Space
1. Terra Zone
2. Hydro Zone
Rooftop Communal Space
3. Meeting Rooms
4. Shower & Toilet
5. Female Changing Room
6. Male Changing Room
7. Gymnasium
8. Swimming Pool
9. Pool Deck
10. Water Jet Corner
11. Chill-out Zone
12. Sky Bridge
Additional Items
a) Grease Trap
• For all Restaurant units
b) Floor Trap
• For all Shop and Office units
c) Air-Conditioning
• For Shop and Restaurant Common Areas: Air-conditioning provided
• For Shop, Restaurant and Office: Split air-conditioning system provided
e) Water Supply
• For Shop, Restaurant and Office: Incoming water supply provided with individual metering
Notes:
1) The brand and model of all equipment supplied shall be provided subject to market availability and at the sole discretion of the Vendor.
2) Layout/location of fan coil units, electrical points, telephone points and door swing positions are subject to Architect’s sole discretion and final design.
3) The Purchaser is liable to pay annual fees, subscription fees and such other fees to the Starhub Cable Vision Ltd (SCV) and/or Internet Service Provider (ISP) or any other relevant party or any other relevant authorities. The Vendor is not responsible for making arrangements with any of the said parties for the service connection for their respective subscription channels and/or Internet access.
4) If the Purchaser requires Internet access, the Purchaser will have to make direct arrangements with the Internet Service Provider and/or such relevant entities/ authorities for Internet services to the Unit and to make all necessary payments to the Internet Service Provider and/or the relevant entities/ authorities.
5) Where warranties are given by the manufacturers and/or contractors and/or suppliers of any of the equipment and/or appliances installed by the Vendor at the Unit, the Vendor shall assign to the Purchaser such warranties at the time when possession of the Unit is delivered to the Purchaser.
6) For cyclical maintenance work to be carried out to the building façade, owners shall allow access to the maintenance team.
7) While every reasonable care has been taken in preparing this website and the plans attached, the developer and its agents cannot be held responsible for any inaccuracies therein. All statements, specifications and plans are believed to be correct but not to be regarded as statements or representations of fact. Visual representations, illustrations, photographs and renderings are intended to portray only impressions of the development and cannot be regarded as representation of facts. Photographs or images contained in this website do not necessarily represent as built standard specifications. All information and specifications are current at the time of press and are subject to change as may be required and cannot form part of an offer or contract. All plans are subject to any amendments approved by the building authorities. Floor areas are approximate measurements and subject to final survey. The choice of brand and model of fittings, equipment, installation and appliances supplied shall be at the sole discretion of the Vendor.